  "query": "Tata Steel UK Port Talbot EAF project news May 2026 construction cost trends NEC4 contract budget benchmarks",
  "claims": [
    {
      "claim": "The construction of the new electric arc furnace at Port Talbot is scheduled to take place between summer 2025 and late 2027.",
      "verbatim_quote": "Constructing new steelmaking technology Summer 2025 – late 2027",
      "source_url": "https://www.tatasteeluk.com/sites/default/files/pimcore_doc/tata-steel-uk-senedd-2026-manifesto-february-2026.pdf",
      "relevance": "high"
    },
    {
      "claim": "The total investment for the Port Talbot transformation project is £1.25 billion, which includes £500 million in support from the UK government.",
      "verbatim_quote": "Tata says it is spending £1.25bn to transform the site to greener steelmaking, backed with £500m from the UK government",
      "source_url": "https://www.bbc.com/news/articles/crl0176kz6po",
      "relevance": "high"
    },
    {
      "claim": "The electric arc furnace start-up phase is projected to occur between late 2027 and 2028.",
      "verbatim_quote": "Electric Arc Furnace start-up phase Late 2027 – 2028",
      "source_url": "https://www.tatasteeluk.com/sites/default/files/pimcore_doc/tata-steel-uk-senedd-2026-manifesto-february-2026.pdf",
      "relevance": "high"
    },
    {
      "claim": "The new electricity connection for the project is expected to go live in late 2027.",
      "verbatim_quote": "New electricity connection goes live Late 2027",
      "source_url": "https://www.tatasteeluk.com/sites/default/files/pimcore_doc/tata-steel-uk-senedd-2026-manifesto-february-2026.pdf",
      "relevance": "medium"
    },
    {
      "claim": "Upgrades to steel mills and continuous casters are scheduled from late 2024 through 2027.",
      "verbatim_quote": "Upgrades to steel mills and continuous casters Late 2024 – 2027",
      "source_url": "https://www.tatasteeluk.com/sites/default/files/pimcore_doc/tata-steel-uk-senedd-2026-manifesto-february-2026.pdf",
      "relevance": "medium"
    }
  ],
  "market_context": "- [HIGH] The construction of the new electric arc furnace at Port Talbot is scheduled to take place between summer 2025 and late 2027. (source: https://www.tatasteeluk.com/sites/default/files/pimcore_doc/tata-steel-uk-senedd-2026-manifesto-february-2026.pdf)\n- [HIGH] The total investment for the Port Talbot transformation project is £1.25 billion, which includes £500 million in support from the UK government. (source: https://www.bbc.com/news/articles/crl0176kz6po)\n- [HIGH] The electric arc furnace start-up phase is projected to occur between late 2027 and 2028. (source: https://www.tatasteeluk.com/sites/default/files/pimcore_doc/tata-steel-uk-senedd-2026-manifesto-february-2026.pdf)\n- [MEDIUM] The new electricity connection for the project is expected to go live in late 2027. (source: https://www.tatasteeluk.com/sites/default/files/pimcore_doc/tata-steel-uk-senedd-2026-manifesto-february-2026.pdf)\n- [MEDIUM] Upgrades to steel mills and continuous casters are scheduled from late 2024 through 2027. (source: https://www.tatasteeluk.com/sites/default/files/pimcore_doc/tata-steel-uk-senedd-2026-manifesto-february-2026.pdf)"
}